District Court In Alabama Dismisses CWA Citizen Suit Claims Where 60-Day Notice Letter Fails To Identify Correct Date Of Alleged Violation

Posted by in Clean Water Act, Environmental Litigation on January 22, 2018

In Black Warrior Riverkeeper, Inc. v. Metro Recycling, Inc., 2017 U.S. Dist. LEXIS 207011 (ND AL, December 18, 2017), the District Court granted defendant’s Motion to Dismiss plaintiffs’ claims brought under the citizen suit provisions of the Clean Water Act for failure to comply with the jurisdictional prerequisite to bringing such a suit:  a sufficient Notice of Intent To Sue pursuant to 33 U.S.C. § 1365(b)(1)(A) and 40 C.F.R. § 135.3 (“60-Day Notice Letter”).  In addition, the District Court dismissed plaintiffs’ claims seeking to enforce a Consent Decree between plaintiffs and the defendant for lack of subject matter jurisdiction.

In Metro Recycling, plaintiffs alleged they witnessed a discharge from the landfill formerly operated, and in the process of being closed, by defendant Metro Recycling.  Pursuant to a Consent Decree between the parties, defendants were to fulfill the requirements of a Modified Closure Plan as well as construct a retention basin that would capture run-off from the landfill in a manner that would prevent additional sediments and contamination from entering an adjacent waterway.  While the alleged discharge from the landfill’s retention basin occurred on January 28, 2016, sample results were returned on February 3, 2016 showing levels of Total Suspended Solids in excess of the limits allowed in the Consent Decree.  The parties agreed the plaintiffs’ 60-Day Notice Letter stated defendant’s alleged violation took place on February 3, 2016 when the actual date of the alleged violation was January 28, 2016.  On this basis, defendant sought to dismiss plaintiffs’ CWA claims for failure to provide a legally sufficient 60-Day Notice Letter in violation of 33 U.S.C. § 1365(b) and 40 C.F.R. § 135.3.

As an initial matter, the District Court affirmed that compliance with the 60-Day Notice Letter requirement was a jurisdictional prerequisite to the filing of a citizen suit under the Clean Water Act.  Citing Eleventh Circuit authority, the Court held, “‘the 60-day notice requirement of 33 U.S.C. § 1365(b) is a mandatory condition precedent to the filing of a citizen suit under the Clean Water Act.’  Nat’l Envtl. Found. v. ABC Rail Corp., 926 F.2d 1096, 1097 (11th Cir. 1991).  ‘If a plaintiff fails to comply with this notice requirement where it is applicable, the district court is required to dismiss the action.’  Id. at 1097-98.”  Metro Recycling, *8.

The District Court then addressed the appropriate standard of review, noting the somewhat contradictory nature of adhering to the Eleventh Circuit’s mandate to strictly construe compliance with the notice requirements of 40 C.F.R. § 135.3 which, in turn, require only that the 60-Day Notice Letter “‘include sufficient information to permit the recipient to identify…the date or dates of such violation.’”  Metro Recycling, *10.  While the District Court noted the specific issue of an erroneous date of violation had not been addressed by the Eleventh Circuit, it found, consistent with a strict construction, that the 60-Day Notice Letter did not provide “sufficient information” to the defendant as the stated date of violation was wrong.  On this basis, the Court granted the defendant’s motion to dismiss the Clean Water Act claims.  The District Court made this ruling despite the fact defendant was actually present during plaintiffs’ testing and had actual knowledge of the date of violation.

The District Court also dismissed plaintiffs’ claim to enforce the Consent Decree itself for lack of subject matter jurisdiction.  Plaintiffs argued that, while the Order affirming the Consent Decree expressly stated the District Court was to retain jurisdiction for one year (and that year had passed), the Order also provided the Court will enforce the settlement between the parties as reflected in the Consent Decree.  As the Consent Decree stated the Court was to retain jurisdiction to resolve disputes that might arise thereunder, plaintiffs argued the Order bestowed ancillary jurisdiction on the District Court.  The District Court disagreed, noting the Consent Decree language conflicted with the Order’s express limitation on the Court’s retention of jurisdiction.  Holding the specific jurisdictional language in the Order took precedence, the District Court granted the defendant’s motion to dismiss plaintiffs’ claim to enforce the Consent Decree for lack of subject matter jurisdiction.

District Court In California Denies Defendant’s Motion To Dismiss CWA Citizen Suit, Finding 60-Day Notice Letter Sufficient And Claims Adequately Alleged

Posted by in Clean Water Act, Environmental Litigation, Stormwater on January 22, 2018

In Coastal Envtl. Rights Found. v. Am. Recycling Int’l, Inc., 2017 U.S. Dist. LEXIS 202649 (SD CA, December 8, 2017), the District Court denied defendant’s Motion to Dismiss plaintiff’s claims brought under the citizen suit provision of the Clean Water Act.  Defendant argued that plaintiff failed to comply with the jurisdictional prerequisite to bringing such a suit:  a sufficient Notice of Intent To Sue pursuant to 33 U.S.C. § 1365(b)(1)(A) and 40 C.F.R. § 135.3 (“60-Day Notice Letter”).  In addition, defendant claimed that it had voluntarily stopped the conduct alleged to constitute certain of the Clean Water Act violations, rendering those claims moot.  Finally, defendant sought dismissal of several of plaintiff’s claims under Federal Rule of Civil Procedure 12(b)(6) for failure to state a claim.  The District Court denied defendant’s motion to dismiss on all grounds.

In Am. Recycling, both plaintiff, a California non-profit, and defendant, a fourteen-acre automobile salvage business, were located in North San Diego County.  Plaintiff alleged that defendant’s storm water discharges polluted the San Luis Rey River and impaired its members’ use and enjoyment of the river.  Specifically, plaintiff alleged that defendant’s operations, management practices and pollution control protocols resulted in contaminated storm water entering the storm water conveyance system or discharging directly to the San Luis Rey River.  In support, plaintiff alleged storm water sampling data from May 2016 showed levels of various parameters in excess of the relevant water quality criteria in violation of the Clean Water Act and requirements of California’s NPDES General Permit for Storm Water Discharges Associated with Industrial Activities (“Permit”).

The District Court first examined defendant’s motion to dismiss for lack of subject matter jurisdiction under FRCP 12(b)(1).  As its initial ground, defendant argued that plaintiff’s 60-Day Notice Letter was inadequate for two reasons:  failing to identify plaintiff’s contact information and failing to identify the industrial activities upon which plaintiff’s claims are based.  The District Court rejected the first argument as the 60-Day Notice Letter did identify plaintiff by name, assert that plaintiff was represented by counsel, provide contact information for that counsel and request all communications be handled through counsel.  Moreover, the District Court noted that, since plaintiff and its counsel shared the same contact information, the technical requirements of 40 C.F.R. § 135.3 were met.  Regarding defendant’s second argument, the District Court found that it ran contrary to the Notice itself which did, in fact, identify the nature of defendant’s facility and relevant SIC code.  Moreover, based on defendant’s knowledge of its own operations, it could not plausibly claim to be unaware of the relevant activities and responsible person or persons.  Finally, the Court looked to defendant’s post-60-Day Notice Letter storm water sampling as evidence that defendant understood “at least some” of plaintiff’s allegations regarding its inadequate monitoring and reporting program.

The defendant’s second ground for its motion to dismiss for lack of subject matter jurisdiction –mootness — was based on its claim that its voluntary cessation of conduct rendered a portion of plaintiff’s action moot as wholly past violations.  The District Court rejected this argument too, finding that plaintiff adequately pled these claims as “continuous or intermittent” Permit violations for this initial stage of proceedings.  Moreover, defendant failed to meet its heavy burden to show that the behavior in question could not reasonably be expected to recur based simply on two post-60-Day Notice Letter storm water sampling events.

Lastly, the District Court turned to defendant’s motion to dismiss several of plaintiff’s Permit violation claims under FRCP 12(b)(6) for failure to state a claim.  The District Court upheld each of plaintiff’s claims, finding plaintiff had adequately alleged the specific Permit violation at issue in each claim, including allegations of defendant’s failure to implement adequate Best Management Practices to comply with the Permit’s effluent limitations, failure to ensure its storm water discharges do not violate the Permit’s receiving water limitations, and failure to implement an adequate Storm Water Pollution Prevention Plan and Monitoring & Reporting Program.

Most notably, the District Court affirmed that plaintiff adequately alleged a violation of the Permit’s Level 1 Exceedance Response Action requirements for exceedances of copper and zinc despite the fact the Permit did not specifically require sampling for those constituents.  However, the Permit did require defendant to sample additional parameters to determine parameters on a “facility-specific basis that serve as indicators of the presence of all industrial pollutants identified in the pollutant source assessment” which must include “the pollutants likely to be present in industrial storm water discharges.”  Am. Recycling, *29.  As plaintiff alleged that copper and zinc had been “historically found at the Facility” and were “common pollutants” found at industrial facilities, the District Court held it was reasonable to interpret the Permit as requiring defendant to sample, analyze and address exceedances of common pollutants in its storm water that defendant should reasonably be aware of, including copper and zinc.  Am. Recycling, *30.  In addition, the District Court pointed to the fact that the defendant actually did analyze its storm water for copper and zinc.  Therefore, in light of the Permit terms and plaintiff’s allegations, plaintiff adequately pled that the defendant was required to compare its sampling results with the limitations set forth in the Permit and then take the required action to address the exceedances.  As defendant allegedly failed to do this, plaintiff adequately alleged a Permit violation.

Based on the foregoing, the District Court denied defendant’s Motion to Dismiss in its entirety.

Ninth Circuit Holds District Courts Must Engage In An Independent Substantive Evaluation Of CERCLA Consent Decrees And May Not Afford A State Agency The Same Level Of Deference As EPA

Posted by in CERCLA on August 8, 2014

Nancy Wilms, Esq. and Michael Einhorn, Esq.

In State of Arizona v. Raytheon Co.. et al., Case No. 12-15691, 2014 U.S. App. LEXIS 14993 (9th Cir. Aug. 1, 2014), the Ninth Circuit reaffirmed the requirement that district courts engage in meaningful substantive review of consent decrees under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”) to determine if there is a rational relationship, based on sufficient evidence, between the proportion of liability attributable to each settling party and the proportion of total costs to be paid by such party under the agreement. Although the required review to be undertaken by the district court is based on its previous opinion in United States v. Montrose Chem. Corp. of Cal., 50 F.3d 741, 747 (9th Cir. 1995), in Arizona v. Raytheon, the Ninth Circuit addresses an issue not present in Montrose: the level of deference to be accorded a state agency where it, not EPA, is the proponent of a proposed consent decree under CERCLA. In these situations, the Ninth Circuit held the required Montrose review will necessarily involve additional scrutiny by the district court to reflect the reduced deference afforded the judgment of the particular state agency involved.

At issue in Arizona v. Raytheon are costs to clean up contamination from a landfill investigated by the Arizona Department of Environmental Quality (“ADEQ”) under CERCLA and its Arizona state law counterpart, the Arizona Water Quality Assurance Revolving Funds (“WQARF”). A group of PRPs (the “Settling Parties”) approached ADEQ regarding early settlements pursuant to CERCLA § 113(f)(2), which would provide the Settling Parties with releases of liability for contribution claims.   In response, ADEQ sent early settlement offers to the Settling Parties requiring them to pay damages in exchange for ADEQ’s releasing them from liability to the state and third parties, including non-settling PRPs at the site.

To obtain judicial approval of the consent decrees, as required by CERCLA § 113(f)(2), the State of Arizona (the “State”) brought an action under CERCLA and WQARF against the Settling Parties and filed a motion seeking approval of the consent decrees. Thereafter, ADEQ sent public notice of the proposed consent decrees with the Settling Parties, to which certain non-settling PRPs (“Non-Settling Parties”) provided comments objecting to the settlement. The State then filed a motion seeking approval of the consent decrees, asserting that the liability of each Settling Party was de minimis, amounting to less than 0.2% of the $75 million estimated clean up costs.

Since non-settling PRPs may bear the costs if early settlements are disproportionately low, the Ninth Circuit has previously held that non-settling PRPs have standing to intervene to oppose entry of consent decrees in CERCLA actions because the public notice and comment procedure is insufficient on its own to protect the interests of non-settling PRPs. United States v. Aerojet Gen. Corp., 606 F.3d 1142, 1152-1153 (9th Cir. 2010). Accordingly, the district court in this case permitted the Non-Settling Parties to intervene, over the objections of the State.

After intervention, the Non-Settling Parties opposed the State’s motion for entry of the consent decrees, relying on Montrose’s holding that a district court must independently determine whether consent decrees are substantively “fair, reasonable, and consistent with CERCLA’s objectives,” and arguing that the State had not proffered sufficient evidence for the district court in this case to make such a determination. The district court disagreed; it approved the consent decrees, and the Non-Settling Parties brought an appeal to the Ninth Circuit.

The Ninth Circuit vacated and remanded the district court’s approval of the consent decrees, concluding that the district court “failed to independently scrutinize the terms of the agreements” and “afforded undue deference to the ADEQ.” Arizona v. Raytheon, 2014 U.S. App. LEXIS 14993 at *11-12. The Ninth Circuit stated that it previously provided the proper legal standard for reviewing CERCLA agreements in Montrose, which “requires that the district court ‘gauge the adequacy of settlement amounts to be paid by settling [parties]’ by engaging in a comparative analysis” of each party’s estimated liability with its settlement amount relative to the estimated remedial costs. Arizona v. Raytheon, 2014 U.S. App. LEXIS 14993 at *18, quoting Montrose, at 747. The Ninth Circuit Court cited with approval a First Circuit opinion holding courts must determine that CERCLA agreements apportion liability based on rational estimates of comparative fault, taking into consideration how much harm each PRP has done. Arizona v. Raytheon, 2014 U.S. App. LEXIS 14993 at *15-16, citing United States v. Charter Int’l Oil Co., 83 F.3d 510, 521 (1st Cir. 1996).

Relying on these authorities, the Ninth Circuit stated that it is not enough for there to be sufficient information in the record for the district court to evaluate the adequacy of CERCLA settlements. Instead, the Ninth Circuit expressly held that the “district court must actually engage with that information and explain in a reasoned disposition why the evidence indicates that the consent decrees are procedurally and substantively ‘fair, reasonable, and consistent with CERCLA’s objectives.’” Arizona v. Raytheon, 2014 U.S. App. LEXIS 14993 at *17, citing Montrose, at 748. Without this, the Court explained, an appellate court cannot determine whether a district court abused its discretion in approving a CERCLA settlement.

Here, the Ninth Circuit found the district court did not engage in the analysis required by Montrose but simply deferred to the ADEQ’s representation that the settlements were fair and reasonable. Indeed, the district court provided only a footnote regarding the State’s estimate of remedial costs and each Settling Party’s share of liability, at the same time admitting that the State did not provide any evidence supporting its judgment or information for the court to independently confirm the Settling Parties’ entitlement to de minimis contributor status. Accordingly, the Ninth Circuit held that the district court failed to substantively assess the adequacy of the agreements and to provide a reasoned explanation for its decision. Arizona v. Raytheon, 2014 U.S. App. LEXIS 14993 at *18-19.

In support of its cursory substantive review, the district court stated in its order that it would not second guess ADEQ, holding it was required to defer to a state agency’s judgment unless it was arbitrary and capricious. The Ninth Circuit disagreed, stating that district courts should not give the same deference to a state agency, such as ADEQ, as that afforded federal agencies regarding the interpretation of federal laws such as CERCLA. Accordingly, the Ninth Circuit held that the district court in this case erred by deferring to the state’s judgment to the same decree as it would have a federal agency. The majority’s opinion expressly holds that while courts may give “some deference” to a state agency’s environmental expertise regarding issues within the scope of that expertise, the state agency is not entitled to deference concerning its interpretation of federal law, including CERCLA’s mandate. Arizona v. Raytheon, 2014 U.S. App. LEXIS 14993 at *24. The precise level of deference to be afforded a state was left undefined by the Ninth Circuit, but is to be assessed by the district court on a case by case basis and may vary from state to state. In the end, however, the Ninth’s Circuit’s decision did not turn on the deference issue, as the Court made it clear that even if the EPA had been a party to the proposed consent decrees at issue, its ruling would have been the same as the district court failed to adhere to the Montrose requirement to “independently scrutinize” the agreements at issue regardless of whether entered by a federal or a state agency.

The Arizona v. Raytheon decision is notable for its unequivocal affirmation of its nearly two decades old opinion in Montrose, but even more so for its enunciation that the required “independent scrutiny” of a settlement must now take into consideration the appropriate level of deference to be afforded the agency proponent of the consent decree at issue. Non-settling PRPs who oppose entry of a consent decree may rely on this opinion to challenge whether a district court engaged in the required Montrose analysis, including an independent substantive evaluation of the respective liabilities of the settling parties in light of their contribution to remedial costs, demanding even more stringent standards for evaluation in cases of state-sponsored settlements commensurate with a particular state agency’s entitlement to deference. As a result, the Arizona v Raytheon decision provides additional support to non-settling parties seeking to challenge entry of CERCLA settlement agreements sponsored by state agencies and, on the flip side, requires significantly more effort to be expended by settling parties to present evidence sufficient to convince the court, after independent evaluation, that their agreements should be judicially approved.

Ninth Circuit Holds Wood Preservative from Utility Poles Discharged into the Environment does not Violate the Clean Water Act or RCRA

Posted by in Clean Water Act, Emerging Issues, Resource Conservation and Recovery Act, Stormwater on July 1, 2013

Nancy Wilms and Michael Einhorn

In Ecological Rights Foundation v. Pacific Gas and Electric Company, 713 F.3d 502 (9th Cir. April 3, 2013), the Ninth Circuit panel affirmed the dismissal of a citizen suit alleging utility poles discharged wood preservative containing pentachlorophenol (“PCP”) into the environment in violation of the Resource Conservation and Recovery Act (“RCRA”) and the Clean Water Act (“CWA”).   Based on the allegations of the complaint, the court held PCP-based wood preservative that escapes the poles was not a “solid waste” under RCRA.  It also held stormwater runoff from the utility poles was neither a “point source discharge” nor “associated with industrial activity,” and therefore does not violate the CWA.

Preservative that escapes through “normal wear and tear” is not “solid waste” under RCRA

To establish an “imminent and substantial endangerment” citizen suit under RCRA, a plaintiff must establish three things:  (1) the defendant has been or is a generator or transporter of solid or hazardous waste, or is or has been an operator of a solid or hazardous waste treatment, storage or disposal facility; (2) the defendant has “contributed” or “is contributing to” the handling, storage, treatment, transportation, or disposal of solid or hazardous waste; and, (3) the solid or hazardous waste in question may present an imminent and substantial endangerment to health or the environment. 42 U.S.C. § 6972(a)(1)(B).  In this case, which focused on the third prong, the Ecological Rights Foundation (“ERF”) did not allege the PCP-based wood preservative at issue is “hazardous waste.”  Therefore, the Ninth Circuit found the case turned on the issue of whether that preservative is “solid waste” within the meaning of RCRA.

The Ninth Circuit found RCRA’s statutory definitions of “solid waste” and “disposal” were too ambiguous to help decide whether “solid waste” includes wood preservative that escapes from utility poles.  42 U.S.C. §§ 6909(3) and (27); see also 42 U.S.C. § 6901(a)(2).  The court then turned to RCRA’s legislative history, and found “RCRA covers ‘waste by-products of the nation’s manufacturing processes,’ as well as manufactured products ‘themselves once they have served their intended purposes and are no longer wanted by the consumer.’” ERF v. PG&E, 713 F.3d at 515, citing H.R. Rep. No. 94-1491(I), at 2.

The court explained ERF was concerned not with wood preservative that is in or on the utility poles, because there the preservative is clearly being put to its intended use as a general biocide.  Instead, ERF was concerned with wood preservative that leaks from or otherwise escapes the utility poles.  The Ninth Circuit held such escaping preservative is neither a manufacturing waste by-product nor a material that the consumer (in this case defendants PG&E and Pacific Bell as owners of the utility poles) no longer wants and has disposed of or thrown away.  The Ninth Circuit concluded PCP-based wood preservative that escapes from treated utility poles through normal wear and tear, while the poles are in use, is not “automatically” a RCRA “solid waste.”[1]

The court supported its holding by citing a Second Circuit opinion which held pesticides are not being “discarded” when sprayed into the air consistent with their intended purpose.  ERF v. PG&E, 713 F.3d at 515-516, citing No Spray Coal., Inc. v. City of New York, 252 F.3d 148, 150 (2d Cir. 2001).  The Ninth Circuit explained that, like the pesticide example, the application of wood preservative to utility poles furthers the intended purpose of those poles.  While ERF argued wood preservative that escapes from utility poles is no longer serving its intended use, the court disagreed, reasoning wood preservative that falls to the base of a utility pole still serves its intended purpose by inhibiting the growth of vegetation, fungi, and other organisms.  The court further supported its decision by noting EPA treats spent munitions under RCRA in the same way – as having served their intended purpose rather than being discarded, citing Military Munitions Rule: Hazardous Waste Identification and Management; Explosives Emergencies; Manifest Exemption for Transport of Hazardous Waste on Right-of-Ways on Contiguous Properties, 62 Fed. Reg. 6,622, 6,630 (Feb. 12, 1997) (codified at 40 C.F.R. § 266.202).  In addition, the Ninth Circuit noted EPA approved the use of PCP as a wood preservative for utility poles, railroad ties and pilings under the Federal Insecticide, Fungicide, and Rodenticide Act while regulating certain categories of materials containing PCP, including “wastes” from PCP manufacturing processes and discarded unused formulations containing PCP.  ERF v. PG&E, 713 F.3d at 516-517, citing 7 U.S.C. §§ 131-136y; 40 C.F.R. § 261.31(a)(Table — F021, F027, F032), 261.32 (Table — K001).

Finally, the Ninth Circuit stated “common sense” compels its decision because accepting ERF’s argument would lead to untenable results.  The court noted that as of 2008, there were 36 million utility-owned wood poles in the United States treated with PCP, so requiring their replacement defies reason.  In fact, accepting the plaintiff’s argument might lead to extreme results as everything from railroad ties to lead paint that naturally chips away from houses could also qualify as “solid waste” and thus be potentially actionable under RCRA.

However, while the Ninth Circuit expressly decided “wood preservative that escapes from wooden utility poles as those poles age has not itself been ‘discarded’ and therefore is not a ‘solid waste,’ under RCRA” it also suggested different allegations could lead to a different result:  “we do not decide  whether or under what circumstances PCP, wood preservative, or another material becomes a RCRA ‘solid waste’ when it accumulates in the environment as a natural, expected consequence of the material’s intended use.” ERF v. PG&E, 713 F.3d at 518. 

Utility poles are not “point sources” or “associated with industrial activity” under CWA

Under the CWA, a “point source” is defined as any discernible, confined and discrete conveyance, including but not limited to any pipe, ditch, channel, tunnel, conduit, well, . . or vessel or other floating craft, from which pollutants are or may be discharged.”  33 U.S.C. § 1362(14).  The Ninth Circuit found the ERF allegations of generalized stormwater runoff were insufficient to establish that the utility poles were point sources and rejected ERF’s argument the utility poles are themselves “conveyances” as unsupported by case law.  The court noted ERF failed to allege the PCP-based preservative went directly into the waters of the United States or flowed into discrete conveyances and, from there, into the waters of the United States, and the court upheld the district court’s dismissal without leave to amend to add these allegations.  As a result, it is unknown what impact such allegations would have had on the Ninth Circuit’s ruling.

The Ninth Circuit also found dismissal of the CWA claim proper as stormwater runoff from the utility poles is not “associated with industrial activity” for four reasons.  First, a utility pole is not directly related to manufacturing, processing or raw materials storage at an industrial plant.  40 C.F.R. § 122.26(b)(14).  In reaching this holding, the Ninth Circuit applied Decker v. Northwest Envtl. Def. Ctr., 133 S. Ct. 1326, 1330 (U.S. 2013), where the Supreme Court held discharges of channeled stormwater runoff from logging roads were not “associated with industrial activity.”

Second, the Standard Industrial Classification system used in the Code of Federal Regulations to define the industrial activities it covers does not include utility poles.  See 40 C.F.R. § 122.26(b)(14)(ii)–(iii), (vi), (viii), (xi).  Third, EPA included “steam electric power generating facilities” in the definition of “industrial activity,” but rejected including “major electrical powerline corridors” in the regulation. See 40 C.F.R. § 122.26(b)(14)(vii).  Based on this distinction, the Ninth Circuit found it reasonable to conclude EPA did not intend to include utility poles in the definition either.

Finally, the Ninth Circuit reasoned if runoff from utility poles were a discharge associated with industrial activity, many other commonplace things, such as playground equipment, bike racks, mailboxes, traffic lights, billboards and street signs would arguably require stormwater runoff regulation which could lead to an “absurd result.”

_____________________________________________________________________________

[1] The court emphasized its holdings turned on the particular allegations of ERF’s complaint and circumstances may exist wherein wood preservative released into the environment through normal wear and tear could be considered to be a “solid waste.”